Evans had another week of warm weather and mostly dry days. Contractors continued to pour concrete at the intersection. Weather permitting, crews hope to finish the concrete pouring by the middle of next week and the current forecast is for warmer and drier days next week! A curing period will be needed to strengthen the concrete once pouring is complete. The irrigation main is also being installed in the medians and sides of the road for landscaping. Project Updates: This Week: Week of July 17th - The inner circle of the roundabout concrete continues being poured.
- Irrigation main instillation for the medians.
- Topsoil placement for landscaping.
- Delivery of boulders for landscaping.
Next Week: Week of July 24th (WEATHER PERMITTING) - Compete concrete pouring.
- Concrete curing period.
- Boulder placement.
Subscribe to our youtube page to see video of the project! Detour Routes:
|