The Independence Day holiday and rainy weather halted most of the work at the roundabout this week. As the forecast looks better next week, contractors are hopeful to begin moving full steam ahead again. Extra crews will be on hand to get as much as they can done with the improved (forecasted) weather. Project Updates: This Week: Week of July 3rd - Weather delayed many of the planned work this week.
- Dewatering the road to ensure it kept form.
Next Week: Week of July 10th (WEATHER PERMITTING) - Pouring the raised median.
- Finishing the curb and sidewalks to include all tie-ins.
- Concrete paving at the intersection.
Subscribe to our youtube page to see video of the project! Detour Routes:
|